Hi there,
I have BE2010 R3 and set up a few jobs, full and diff. The target is a UNC share that is always available. On that share I have created folders, for each job 1 folder. The target is a sata disk. The disk will be changed with another every monday. So full back-ups run in the weekend.
When I run the jobs manualy, they run fine. When leaving them scheduled, the fail.
Drive and media mount requested: 25-08-2013 01:00:00
V-79-57344-33039 - Error - Mount failed.
User canceled a Physical Volume Library operation.
The fulls and diffs have al the same media set, set to overwrite protection period 6 days and append period Infinite - Allow append.
The fulls and diffs are targeted to their own B2D on that drive, job set to Append to media, overwrite if no appendable media is available.
I did some searching and fount that the Append setting should be set to Overwrite.
I do not use a Device Pool since I have some enough articles that it also works like this setup.
So what is going wrong? For now I have them setup to Overwrite but do I need to set this up also with the Diff jobs? I don't wan't him to overwrite my diff every day. That should be kept for 1 week.
My goal is:
1. Run full jobs in the weekend and change the disk (UNC) every monday morning. It may ovewrite the old backup.
2. Run diff jobs every working day. Should overwrite after 1 week.
Is my setting wrong and if so, what should I change?
Thanks.